Vietnam’s
economic dynamism over the past two decades has given rise to a swift increase
in energy demand. According to WB, power demand is expected to rise by
approximately 16% annually from 2008 to 2010.
Vietnam’s
economic dynamism over the past two decades has given rise to a swift increase
in energy demand. According to the World Bank, power demand is expected to rise
by approximately 16 per cent annually from 2008 to 2010 and continue to
increase at 11 per cent, per year between 2011 and 2015.
It is no secret that the Vietnamese government has been struggling
to keep up with supply requirements. The country experienced electricity
shortages of 1.1 billion kWh in 2006 and 6.6 billion kWh in 2007 with
load-shedding during the dry season. Concerns remain as many power projects
have been delayed in becoming operational while Electricity of Vietnam (EVN)
recently indicated to the government that it would have to delay the
implementation of up to 13 power projects due to lack of capital.
It is expected that Vietnam
will increasingly have to rely on foreign financing and expertise in addressing
the situation and foreign-financed independent power producers (IPPs) will be
required. Unlike in China,
where surging demand in the 1990s was met with large amounts of capital
invested by domestic players, it is expected that Vietnam will have to rely on a
substantially higher degree of foreign investment as EVN and local companies
are unable to provide or raise sufficient capital.
Vietnam’s
present capacity comprises electricity generation from hydro and thermal power
plants, with the percentage of coal and gas-fired capacity quickly outstripping
generation capacity from hydro. Nuclear power plants are being mooted and if
they proceed, estimated to be generating electricity by 2020. Renewable energy
projects remain at a nascent stage while there has been an increased interest
recently in wind power projects.
Going forward, a greater percentage of capacity is expected to come from IPPs,
which are owned primarily by state-owned fuel or construction companies (such
as PetroVietnam), as well as those developed through build-operate-transfer
(BOT) projects, a number of which are foreign-owned and financed. There are
currently some foreign-owned thermal power plants (Phu My and Tra Vinh), and a
number of additional projects are in the pipeline.
Out of necessity, the Vietnamese government is promoting independent production
of power. Domestic and foreign-owned IPPs accounted for as much as 24 per cent
of installed capacity in 2006 and this is expected to grow quickly. The World
Bank expects new wholly foreign-owned and financed IPPs to be the largest area
of development in Vietnam’s
power sector over the medium term.
EVN owns or is the majority shareholder of most generation capacity, the transmission
system and the main distribution companies. There are also low voltage
distribution networks owned by independent companies running power to rural and
distant areas of the country.
The Electricity Law
Under Vietnam’s
Electricity Law effective July 1, 2005, the Ministry of Industry and Trade
(MoIT) is in charge of developing and restructuring the power market and
creating the necessary infrastructure. The most important aspect of the
Electricity Law is its provision for a gradual three-stage transition towards
full power market liberalisation as per the “roadmap”.
The Electricity Regulatory Authority of Vietnam (ERAV) was set up in late 2005
to perform the following functions:
(i) issue and enforce electricity licences; (ii) advise the MoIT on market
structure and policy; (iii) propose the market design and develop the necessary
regulatory framework; (iv) oversee the operation of the electricity market; and
(v) ensure balance between long and short term energy balance in Vietnam.
The jury is still out on how ERAV is handling its regulatory role in the Vietnam power
reform process. The scope of its authority is still being determined and its
enforcement powers are still being defined.
Power Development Master Plan VI
The Electricity Law also requires national power development
master plans to be formulated for each 10-year period and include a notional
view towards the following 10-year period. The Vietnamese government set out
its most recent vision for the power sector in its Power Development Master
Plan VI (“Master Plan”). The Master Plan covers 2006 to 2015 and provides an
ambitious strategy to bring the country’s electricity market in line with more
liberalised competitive market standards.
The BOT Decree
Under Vietnam’s
2007 BOT Decree, the government expressly “encourages” investment in
infrastructure facilities including roads, rail, air and sea ports, water and
waste plants, power plants and transmission. Key provisions under the BOT
Decree include:
(i) the “preferred” method of selection of an investor for a BOT contract is
that of an international or domestic tender. However, the direct appointment of
an investor is still permitted in certain circumstances, including where a
project is proposed directly by an investor and where there is only one
investor who satisfies the requirements of pre-qualification; (ii) the minimum
equity requirements range from 10 to 30 per cent of the total investment
capital, depending on the amount of total investment capital; (iii) clearer
provisions on “step-in” rights than its predecessor, although “step-in” rights
remain subject to approval by the government.
There are various incentives for investors undertaking a BOT project. These
include exemption from applicable land use fees or land rent, exemption from
import duties on goods imported to implement the project, as well as
significantly reduced corporate income tax and tax holidays. It may be possible
for investors to negotiate additional incentives for a particular project.
The status of the BOT Decree is currently being revisited and the government is
in the process of issuing a number of amendments to the BOT Decree. At the same
time, the Ministry of Planning and Investment has been charged with adopting
the implementing guidelines for the BOT Decree. Both legal documents are still
under consideration although there seems to be a risk that the further the
discussions concerning the amendments to the BOT Decree are delayed, the longer
it will take to issue the highly relevant implementing regulations.
Equitisation of EVN-owned generation capacity
Equitisation of generation and distribution companies owned by EVN
or its subsidiaries is a key priority of the electricity market reform drive.
The Vietnamese government is pushing to restructure state-owned monopolies such
as EVN into shareholding companies separate from the government to increase
competition, investment and efficiency.
Under Vietnam’s
equitisation scheme, EVN-owned SOEs with power assets are corporatised and
their shares are subsequently sold to private investors. This will typically
involve an IPO on the Ho Chi Minh City or Hanoi stock exchanges.
Government policy dictates that EVN retains at least 51 per cent of the
newly-equitised joint-stock power companies. These companies then enter into
power purchase agreements (PPAs) with EVN to sell their generated power into
the wholesale and, eventually, retail electricity market.
Strategic generation capacity, including multipurpose hydroelectric generation
facilities and any future nuclear plants, will remain fully owned by EVN. To
date, EVN has equitised several power plants and a distribution company and
this process should accelerate in coming years.
Structuring investments
Foreign investment in Vietnam’s power sector can be mainly
structured in one of three ways:
(i) through a BOT contract with the MoIT which is implemented through a
wholly-owned foreign enterprise,
(ii) through a BOT contract with the MoIT which is implemented through a joint
venture with a Vietnamese entity (usually including EVN, but it is also
possible with a private domestic IPP), or
(iii) through the purchase of shares in either an EVN subsidiary being or
having been equitised or a private IPP holding power assets.
Further, Vietnamese law permits a foreign investor to obtain an investment
certificate for an IPP outside the BOT structure (and thus without the
requirement to transfer the power plant at the end of a specified term),
although there has been no precedent to date of a stand-alone foreign-owned
non-BOT project in Vietnam.
The BOT structure has been used successfully in the Phu My 2.2 and Phu My 3
IPPs (see below). This structure provides for a project company to be set up to
enter into a BOT contract with the MoIT and a PPA directly with EVN.
Coal-fired power projects
The majority of Vietnam’s
coal-fired plants are situated in the north of the country. A third IPP project
in BOT form has been approved and AES and Vinacomin, the main state-owned coal,
minerals and mining conglomerate of Vietnam, intend to establish the
1,200 megawatt (MW) Mong Duong II thermal power plant at an estimated
investment cost of about $1.4 billion.
This project has apparently been subject to tendering problems which are still
being settled. One of the larger domestic projects is the 4,400MW Kien Luong
coal-fired plant to be built by local Tan Tao Group, a diversified
infrastructure group. At an estimated total investment cost of $6.7 billion,
Tan Tao has already indicated that it is looking for foreign investors to
participate in the project.
It has also been reported that Vinacomin plans to have seven or eight new
coal-fired power stations generating electricity by 2010, which will add
2,900MW to Vietnam’s
generation capacity. Other coal-fired power plants are being expanded.
Coal-generated power is expected to rise by 20 per cent during the same period.
Gas-fired power projects
Electricity generated from natural gas is bound to increase moving
forward for both supply and environmental reasons. Vietnam has an estimated 400
billion cubic metres of gas reserves.
EVN itself is pushing ahead with development of the O Mon complex with gas
supply from Chevron’s blocks in the SouthWestBasin
gas field. Total increased capacity is expected to be 2,700MW. PetroVietnam has
also invested heavily in the Ca Mau power project, which includes two 720MW
gas-fired combined-cycle turbines supplied with gas from the SouthWestBasin.
Participants in new IPPs in Vietnam
can look to the Phu My projects for guidance and a foundation of experience.
Two of the Phu My power projects are foreign-owned IPPs structured as BOT
projects: Phu My 2.2 and Phu My 3.
The gas-fired combined-cycle generation facility’s fuel is supplied by
PetroVietnam from the Nam Con Son pipeline linking the Lan Tay and Lan Do
undersea gas fields just off the southeast coast.
Commercial banks, including lead arrangers ANZ Investment Bank, SMBC and
Societe Generale, chipped in $100 million, with IDA and ADB providing $75
million and $25 million political risk guarantees respectively. ADB entered
into a back-to-back arrangement for Sovereign Risk Insurance to cover its
guarantee.
The Phu My 2.2 project was the first BOT project in Vietnam to reach financial close.
The project also achieved notoriety for being the first financing in Vietnam with
loan tenors of up to 16 years, and for having the first limited recourse
financing package of such a significant size.
The more recent $412 million Phu My 3 BOT Project, which started commercial
operation in March 2004, was the first IPP to operate in Vietnam.
Project sponsors include a consortium of Kyuden International Corporation and
Sojitz for 33.3 per cent, BP for 33.3 per cent and SembCorp Utilities Pte Ltd.
for 33.3 per cent, using a 3:1 debt to equity ratio. Phu My 3 power plant
provides southern Vietnam
with 716,800KW of electricity.
Interestingly, Phu My 3 sponsors retained the project’s construction and
delivery risks. It will be interesting to see if this aspect will repeat itself
in future IPP projects, such as Nghi Son 2. The PPA between the project company
and EVN has an offtake term of 20 years while the BOT contract between the
Ministry of Industry (now the MoIT) and the project company is for 23 years.
Direct agreements with the state participants followed a very structured format
and effectively bound the Vietnamese parties, which included the State Bank,
EVN, Vietcombank and the provincial peoples’ committee, to a single agreement.
The Vietnamese government provided a foreign law-governed sovereign guarantee
to ensure the financing went forward for Phu My 3. Since the Phu My 3 Project,
however, the government has been reluctant to issue further guarantees apart
from those covering only a small portion of the investment risk.
Together with the government’s reform process and liberalisation of the
electricity market, the Phu My projects potentially serve as benchmarks and
contribute to a more attractive investment environment in Vietnam’s power
sector. Based on the Phu My experience, the Vietnamese government,
international commercial banks and developers will certainly be much more
comfortable with the use of similar BOT structures for foreign investments in
IPPs. Phu My 3 was entirely offshore-financed, whereas future projects will
likely include a domestic component.
The legal regime in place for taking security in Vietnam has since been upgraded and
some international banks now have been approved for onshore banking licences.
Mortgaging of land use rights by a foreign-invested enterprise to a foreign
lender is permitted where the mortgage is made to the lender’s branch in Vietnam (for credit institutions only), but is
not permitted where the foreign lender does not have a foreign bank branch in Vietnam.
According to the World Bank, the government appears to be pursuing an
aggressive IPP development strategy to get more capacity in the system. Given
the perceived opportunities for foreign IPPs, Vietnam has attracted substantial
attention from industry players in recent years.
It has been reported that Sumitomo Corporation is planning to build a 2,640MW
plant in Khanh Hoa province and that SembCorp Utilities intends to develop a
700MW plant in Ho Chi Minh City.
Other industry players, including EDF, International Power, Hong Kong Electric
and others, all appear to be looking at the market.
Despite keen interest, the main issue to date has been that the MoIT has so far
been slow to license any new wholly foreign-owned IPPs to operate in Vietnam and has
been slow in implementing the seemingly aggressive strategy contemplated under
the Master Plan.
This is despite the fact that a number of projects have received support at the
local level. Future foreign-invested power projects include Mong Duong 2, a
1,200MW coal-fired power plant to be developed by US-based AES Corporation in
the form of a joint venture with state-owned Vinacomin and might be approved as
early as the second quarter of 2009 and Nghi Son 2, a 2×600MW coal-fired plant
under the BOT form.
As recently indicated, the MoIT intends to cooperate closely with IFC and World
Bank to develop certain standard documentation for the bidding procedures of
Vietnam’s proposed international tender IPP projects which would include
standard form tender invitations, BOT contracts and so forth.
Continued political will, streamlining of the bureaucratic hurdles to foreign investment,
and appropriate progress towards greater transparency, competition and
privatisation of SOEs will be necessary to achieve Vietnam’s ambitious objectives for
meeting its surging power demand.